Pejeng Kawan, Ubud

Green Harmony, construction log

How the project has moved, entry by entry. Each record has a date, a stage and a source, from the land lease and permits to site photos and handover. The page is updated as new reports arrive. Latest entry: 17 October 2025.

6entries
4site photos
17 October 2025latest entry
  1. Documents

    Updated plot validation

    The project folder holds the land documents and an updated validation dated 17.10.2025. No final PBG/SLF file with a number is in the set, so we do not mark the permit as obtained. The current pack is available on request.

    Source: projects/green-harmony/index.html

  2. Operations

    January–September 2025 results

    Gross income of the four villas $89,229, net owner income $47,415, average occupancy 88.2%. Annualised yield 11.6–18.1% per villa at a $95,000 purchase price. Source: Betterplace monthly reports.

    Green Harmony living room opening onto the pool

    Source: projects/green-harmony/index.html

  3. Operations

    August 2025, peak $7,418

    The best month of the period. Net owner income was $7,418 in August 2025, $6,507 in July and $6,006 in September.

    Green Harmony terrace with a hammock and rice-field view

    Source: projects/green-harmony/index.html

  4. Operations

    January 2025, $4,130 to owners

    Start of the confirmed reporting period. Net owner income across the four villas was $4,130 in January 2025, $1,778 in February and $3,824 in March.

    Source: projects/green-harmony/index.html

  5. Operations

    Rentals begin

    The villas' actual operating period runs from November 2024. Listings are live and owners receive monthly reports from the operator Betterplace.

    Private pool of a Green Harmony villa

    Source: projects/green-harmony/index.html

  6. Handover

    Complex handed over to owners

    Four two-storey 84 m² villas were built turnkey, sold and handed over to owners in Q3 2024. It is DOMA's first delivered complex.

    The four delivered Green Harmony villas by the rice fields

    Source: projects/green-harmony/index.html

Not a public offer. Dates come from documents and site reports. Entries marked as planned are contract deadlines, not completed work.

← Green Harmony project page

Want the reports in full?

Investors get biweekly photo and drone reports in their dashboard. Ask us to show a real report before you decide.