Lodtunduh, Ubud

Mirador Villas, construction log

How the project has moved, entry by entry. Each record has a date, a stage and a source, from the land lease and permits to site photos and handover. The page is updated as new reports arrive. Latest entry: September 2027.

8entries
5site photos
September 2027latest entry
  1. Handover

    Planned villa handover

    Contractual completion in September 2027. Between the PBG and handover lie three stages with signed acts, 30/30/30/10 payments after each act and bi-weekly photo, video and drone reports.

    Source: projects/mirador/index.html

  2. Sales

    Villas 1 and 2 sold

    The project page lists villas 1 and 2 as sold, with five of seven positions available. Status recorded as of November 2026, the deal dates are not published. We confirm availability before booking.

    Aerial rendering of Mirador, seven villas along the canyon

    Source: projects/mirador/index.html

  3. Sales

    Yield models from two operators

    Two management companies, Bali Legend and Betterplace, modelled occupancy, rate and net income in three scenarios. The models are dated August 2026. The base case gives 12.3% net at 84% occupancy and a $125 rate, a forecast, not a guarantee.

    Rendering of the Mirador villa living room and kitchen

    Source: projects/mirador/index.html

  4. Documents

    PBG issued

    PBG no. SK-PBG-510405-06082026-005 was issued on 6 August 2026. Approved use hotel building, 581.69 m² on two floors, zone R3. A copy goes to the buyer and their lawyer for review before the deal.

    Rendering of the seven Mirador villas on the canyon's first line

    Source: build.py

  5. Documents

    Government fee paid

    The government fee for the PBG was paid on 4 August 2026.

    Source: build.py

  6. Documents

    Technical standards approved

    First step towards the PBG. The building's technical standards were approved on 29 July 2026.

    Source: build.py

  7. Documents

    KKPR obtained, PBG in progress

    Issue 1 of the DOMA journal, dated 25 July 2026, recorded the project status. Yellow zone R3, KKPR obtained, PBG in progress, price $139,000, completion September 2027, off-plan.

    Mirador Villas master plan, seven villas along the canyon

    Source: content/journal/2026-07-25.html

  8. Land

    Land leasehold registered

    The Hak Milik land is leased under a 29+10+30 year structure from 04.03.2026. The certificate sits with the notary and the land payment went through escrow.

    Rendering of the Mirador complex by the canyon in Lodtunduh

    Source: sections_glossary.py

Not a public offer. Dates come from documents and site reports. Entries marked as planned are contract deadlines, not completed work.