Infrastructure · Bali

Bali: grid margin of 299 MW over peak load of 1,379 MW

Bali's power system can currently supply 1,678 megawatts, while peak demand reached 1,379 megawatts. A PLN representative in Bali said so on 23 October 2026, adding that a spare margin does not by itself rule out outages.

News of Published in DOMA News: 3 min read

Key points

  • Bali's available power capacity is 1,678 MW, peak load is 1,379 MW, and the difference is 299 MW.
  • PLN warns that reliability also depends on how ready the plants and networks are, not only on the margin.
  • The national power plan (RUPTL) for 2025-2034 foresees about 2.744 GW of new capacity for Bali.
  • These are planned targets through 2034, not capacity that has already been built.
1,678 MWavailable capacity of Bali's power system
1,379 MWrecorded peak load
299 MWgap between capacity and peak load
2.744 GWcapacity planned to be added through 2034

What happened

The communications and corporate social responsibility manager of PLN UID Bali, I Wayan Eka Susana, described the state of the island's power system on Friday, 23 October 2026. PLN, the state electricity company, said the available capacity of Bali's system reaches 1,678 megawatts (MW). Peak load was recorded at 1,379 MW.

The difference between the two figures is 299 MW. According to the PLN representative, the system currently has a spare margin.

Why a margin does not rule out outages

Eka Susana stressed that the size of the margin does not mean outages are impossible. The reliability of supply also depends on how ready the power plants are, on the state of the transmission and distribution networks, and on whether the system can withstand a fault.

In other words, a 299 MW margin shows that on average there is enough capacity, but it does not say how often or where interruptions occur. The source gives no data on that.

Peak load is the highest level of simultaneous electricity use over a period. Plants and networks are designed around it. Available capacity shows what the system can actually deliver, not what is written in plant specifications. Comparing the two figures therefore gives a rough but clear picture.

What PLN plans to build

For future load growth PLN relies on its electricity supply business plan, RUPTL, for 2025-2034. It provides for about 2.744 gigawatts (GW) of additions to the Bali system. Of that, 886.8 MW is renewable energy, 307.5 MW is energy storage and 1,550 MW is gas-fired generation.

Besides plants, the plan includes 885 kilometres of transmission lines and substation capacity of 3,320 megavolt-amperes (MVA). Distribution networks are also to be developed.

Where demand comes from

According to Eka Susana, these steps are needed to get ahead of rising consumption from tourism, property development and electric vehicles. PLN separately mentions the growth of electric transport and says it is preparing the system for electric buses and other electric vehicles.

For a private owner this means load on the grid will grow from new villas and from vehicle charging alike. The source does not say how large that growth will be.

An island-wide figure hides differences between districts. Interruptions may come from a particular line or substation rather than from a general shortage of capacity. So the system-wide margin and the situation on a given street can differ.

An important caveat on the plan's status

PLN itself notes that the added generation and network reinforcement in RUPTL are a phased plan running to 2034. They are not capacity that already exists. Future reliability depends on whether the projects are delivered, whether the infrastructure is ready, and whether supply growth matches load growth.

So the 2.744 GW figure is currently a stated plan, not a fact on the ground.

For residents and businesses the takeaway is cautious. Today there is no general capacity shortfall, but the source does not promise an absence of outages either. The long-term targets for plants and networks will take time and investment, and should be judged as they are delivered.

What happens next

Watch how PLN delivers the RUPTL projects through 2034 and how peak load in Bali changes as electric vehicles and new properties grow in number. The source gives no dates for individual plants or lines.

What it means for investors

When buying a villa, check the connection's contracted power in volt-amperes and the outage history in the area. Work out the cost of a backup power source if uninterrupted supply matters for your property, for example for rentals. If you plan to charge an electric vehicle or air-condition a large area, check that the permitted capacity is enough. The 2034 plan is not yet built, so do not put it into your calculations. We check the connection and capacity when assessing a property.

Open the Bali map

Q&A

Is there enough electricity in Bali now?

PLN says capacity exceeds peak load by 299 MW, but it adds that this does not rule out outages.

Are the 2.744 GW of new capacity already built?

No. They are planned additions under RUPTL through 2034, not operating capacity.

Source
NusaBali, published October 23, 2026, language: Indonesian

Prepared by the DOMA editorial team from public reports, with the original source linked above. This is a news review, not legal or tax advice. Not a public offer.