Infrastructure · Denpasar

Denpasar: 723 of 1,100 piles driven at Bali PSEL waste-to-energy plant

Danantara supervisory board deputy chair Muliaman Hadad toured the PSEL waste-to-energy construction site in South Denpasar on 5 November 2026. The operator said the 1,500-tonnes-a-day plant is planned to be finished within 24 months.

News of Published in DOMA News: 3 min read

Key points

  • Bali PSEL is designed for 1,500 tonnes of waste a day and up to 240 GWh of electricity a year at an average of 30 MW.
  • Piling is done at 723 of 1,100 points, with completion planned for November 2026.
  • The building permit (PBG) and the airport's technical recommendation on building height are already in hand, and construction is planned to take 24 months.
1,500 t/daydesign waste-processing capacity
240 GWhpotential annual electricity output
723 of 1,100piling points completed
700+workers during construction, operator's estimate

Who visited and what was said

On Thursday, 5 November 2026, Muliaman Darmansyah Hadad, deputy chair of the supervisory board of BPI Danantara (the state investment agency), visited the Bali PSEL construction site in South Denpasar. PSEL, Pengolahan Sampah menjadi Energi Listrik, means converting waste into electricity.

Muliaman called progress very good and concrete. He said the project should become a model that other Indonesian regions can copy, and that it should deliver benefits for residents and the economy as well as environmental ones. Representatives of PLN (the state power company) and the provincial and Denpasar city governments attended the meeting.

What is being built and when

Fadli Rahman, president director of PT Daya Energi Bersih Nusantara (Denera), said the plant is designed for 1,500 tonnes of waste a day. Potential output is 240 GWh of electricity a year at an average capacity of about 30 MW. The site covers six hectares and construction is planned to take 24 months.

These are stated project parameters, not actual output. The plant is still under construction.

Permits and work stages

According to the operator, the building permit PBG (Persetujuan Bangunan Gedung) and the airport authority's technical recommendation on building height have been obtained. The basic engineering design is complete and contains 386 drawings. Main machinery and equipment are being ordered and fabricated.

On site, bore pile work has covered 723 of 1,100 points, with completion targeted for November 2026. Foundations for the waste bunker and incinerator are under way and should finish in March 2027. The operator estimates employment at more than 700 people during construction.

The city's position

Denpasar Deputy Mayor I Kadek Agus Arya Wibawa welcomed the visit. He said waste is a challenge that needs commitment and coordinated action from all parties. In his words, processing technology can turn waste from a problem into an energy source that benefits residents. That is his statement, not an assessment of results. Muliaman, for his part, stressed that the project rests on cooperation between regional governments, PLN, investors, the TNI armed forces and other parties. The source does not say who finances which part.

What it means for the area

The project is in South Denpasar, close to districts with many villas and hotels. The source does not describe effects on neighbouring plots and says nothing about noise, odour or traffic. Such questions are normally handled in the project's environmental documents, which the report does not mention.

Construction terms explained

Bore piles are cast-in-place concrete piles: a hole is drilled and then filled with concrete. They form the base for heavy structures such as the waste bunker and the incinerator. Engineering drawings and equipment specifications are needed so machines can be ordered from factories before the site is ready for installation. The source does not give the project cost, the electricity tariff or the commissioning date, so the plant's economics cannot be judged from it.

What happens next

Next milestones in the plan are completion of piling in November 2026 and the bunker and incinerator foundations by March 2027. Watch for published dates for equipment delivery and commissioning.

What it means for investors

If you are considering a villa or land near Suwung and South Denpasar, ask the seller and the local administration for the PSEL project documents and environmental findings. Compare the distance from the property to the site, access roads for waste trucks, and plans for odour and noise. Remember this is a stated plan, not an operating plant. Any risk assessment for your rental income should rest on figures for the specific address.

Open the Bali map

Q&A

What is the capacity of Bali PSEL?

By design, 1,500 tonnes of waste a day and up to 240 GWh a year at an average of 30 MW.

When will construction finish?

The operator cites 24 months. Piling is due in November 2026 and foundations in March 2027.

Source
Antara Bali Ekonomi, published November 6, 2026, language: Indonesian

Prepared by the DOMA editorial team from public reports, with the original source linked above. This is a news review, not legal or tax advice. Not a public offer.